The Federal Government has delivered 1,080 megawatts (MW) of additional electricity transmission capacity under its Presidential Power Initiative (PPI), popularly known as the Siemens power project, leaving 4,460MW outstanding against its 5,540MW target for 2028. The achievement represents just 19.5 per cent of the programme’s targeted additional transmission capacity, raising questions about whether the government can deliver the remaining capacity within the next two years.
The 1,080MW was achieved through the installation of 10 mobile substations and 10 power transformers across 10 locations nationwide.
According to a programme status document obtained from the FGN Power Company, another 984MW is currently under implementation through the first batch of transmission substation upgrades, while projects expected to deliver an additional 3,376MW remain in the pipeline. The figures suggest that although the pilot phase has been completed, most of the programme’s promised transmission capacity is still awaiting implementation, financing and regulatory approvals.
The Siemens power initiative was conceived in August 2018 following the visit of former German Chancellor Angela Merkel to Nigeria. The Federal Government and Siemens subsequently signed an implementation agreement in July 2019. The completed pilot phase involved the installation of 10 power transformers and 10 mobile substations, financed with €60.4 million.
The facilities were deployed across Ajah in Lagos, Ibadan in Oyo State, Sapade in Ogun State, Potiskum in Yobe State, Kwanar Dan-gora in Kano State, Jebba in Niger State, Okene in Kogi State, Apo in Abuja, Ihovbor in Edo State and Amukpe in Delta State. Despite the project’s long gestation, its implementation has suffered repeated delays. Earlier targets of increasing Nigeria’s operational grid capacity to 7,000MW by 2021 and 11,000MW by 2023 were not achieved.
In December 2023, the Federal Government signed an accelerated performance agreement with Siemens Energy to fast-track delivery.
Under the first batch of substation upgrades, the government expects to add 984MW by rehabilitating and upgrading five existing transmission substations. The facilities are located at New Abeokuta in Ogun State, Ayede in Ibadan, Offa in Kwara State, Onitsha in Anambra State and Sokoto in Sokoto State.
Siemens Energy is handling the engineering, procurement and construction of the substation projects. The initiative also includes 16 transmission lines covering 606.5 kilometres of 330kV and 132kV networks, with a combined throughput capacity of 7,140MW.
These comprise 399.5 kilometres of 132kV infrastructure and 207 kilometres of 330kV lines, designed to address bottlenecks preventing electricity generated by power plants from reaching consumers efficiently. Two priority projects are the 38-kilometre 132kV Ajah-Shapaati transmission line and the five-kilometre 330kV Ayede-New Abeokuta line.
The government is targeting completion of these priority projects by May 2027, subject to financing arrangements and other implementation requirements. Although the Federal Government has paid its 15 per cent counterpart funding for the transmission line programme, negotiations on the financing facility are still ongoing.
Financial close is expected in the first quarter of 2027, with delivery of the 16 transmission lines scheduled between the first quarter of 2027 and the fourth quarter of 2028.